Buyer's guides · Cost
How much does commercial solar cost in the UK?
What a 100 kWp+ system really costs per kWp, and why two quotes for the same roof can differ so much.
Written by Harry HainesCEO & Co-Founder, CH Group
Updated · 8 min read
CH Group runs controlled solar tenders for commercial sites of 100 kWp and above.

The short answer
There is no official UK price series for commercial solar above 50 kW. The DESNZ median for 10 to 50 kW systems in 2025/26 is £1,262 per kW, and the data stops there 1.
Installer sources put fully installed, ex-VAT prices at roughly £700 to £1,100 per kWp for systems of 100 kWp and above, falling as size rises. Spirit Energy's 2026 totals work out at £720 to £1,000 per kWp at 250 kWp and £700 to £960 at 500 kWp 2.
Commercial solar is charged at 20% VAT 5, which VAT-registered businesses can usually reclaim 4. Check your position with your accountant.
Figures checked
Key numbers
| Figure | Source | |
|---|---|---|
| Median cost, 10 to 50 kW systems (2025/26, declared net capacity basis) | £1,262 per kW | DESNZ, 28 May 2026 |
| Same band, total installed capacity basis | £1,204 per kW | DESNZ, 28 May 2026 |
| 100 kWp installed range, ex-VAT | £750 to £1,050 per kWp | Spirit Energy, 2026 |
| 250 kWp installed range, ex-VAT | £720 to £1,000 per kWp | Spirit Energy, 2026 |
| 500 kWp installed range, ex-VAT | £700 to £960 per kWp | Spirit Energy, 2026 |
| VAT on commercial solar | 20% (0% is residential and charitable only) | HMRC Notice 708/6 |
| Inverter replacement after 10 to 15 years | £2,000 to £10,000 | OVO, 4 Nov 2026 |
What goes wrong, and what does it cost?
The usual mistake is comparing quotes per kWp when each quote covers a different scope, so the cheapest headline price is often the one with costs left out.
The board is asked to approve a quote nobody can compare. One installer says £720 per kWp, another says £950, and nobody can say why.
The real mistakes behind that gap are specific, and each one costs money.
- Using the wrong benchmark. The DESNZ £1,262 per kW figure is for 10 to 50 kW systems. It is a different size class from a 200 kWp roof, and quoting it as the price of a large roof overstates the cost.
- Believing VAT is 0%. Some installer pages say commercial solar qualifies for zero VAT. HMRC Notice 708/6 limits the 0% relief to residential accommodation and buildings used solely for a relevant charitable purpose 5. On a £200,000 system, assuming 0% hides £40,000 of VAT that your business must pay first and reclaim later, if it is VAT-registered.
- Comparing different scopes. Roof type, scaffolding, the number of inverters and the grid application all move the price. A quote that leaves out scaffolding or the G99 application looks cheaper and is not.
- Ignoring inverter replacement. Inverters typically need replacing after 10 to 15 years, at £2,000 to £10,000 according to OVO 3. A 25-year model that leaves it out is overstated.
- Mixing kWp with kW AC. kWp is the panel (DC) rating. A quote in kW AC describes the inverter output, so the same roof gives two different numbers.
Each mistake is cheap to avoid before signing and expensive to find afterwards. Our guide to how to compare commercial solar quotes shows how to put every quote on one basis.
How much does commercial solar cost per kWp in the UK?
Installer sources quote roughly £700 to £1,100 per kWp ex-VAT for commercial systems of 100 kWp and above, and no official source covers that size.
DESNZ publishes the official UK small-scale solar PV cost data. It is built from the MCS Installation Database, and its size bands stop at 10 to 50 kW 1. It has nothing for a 100 kWp or 500 kWp roof.
DESNZ also reports on two bases. Declared net capacity gives £1,262 per kW for 10 to 50 kW systems in 2025/26. Total installed capacity gives £1,204 per kW. After inflation, the 10 to 50 kW median fell 3% on the first basis and 4% on the second compared with 2024/25.
Above 50 kW, buyers rely on installer ranges. OVO gives £700 to £1,100 or more per kWp for 100 kW and above, with costs correct as of April 2026 3. Solar4Good gives £800 to £850 per kW ex-VAT for a 100 kW system, about £80,000 to £85,000 4. These sources are installers or lead-generation sites with an interest in the sale, and they do not publish the data behind their numbers.
No public source we found gives prices for systems of 1 MW and above, so this guide gives none.
How much does a 100, 250 or 500 kWp system cost in total?
On Spirit Energy's 2026 ranges, a 100 kWp system costs £75,000 to £105,000 ex-VAT, a 250 kWp system £180,000 to £250,000 and a 500 kWp system £350,000 to £480,000.
The price per kWp falls as the system gets larger in Spirit Energy's ranges. The table shows those ranges, with other public sources alongside 2.
| Size | Per kWp (from Spirit Energy totals) | Total installed cost | Other public sources | Best for |
|---|---|---|---|---|
| 50 kWp | £800 to £1,100 | £40,000 to £55,000 | OVO: £660 to £1,200 per kWp; DESNZ 10 to 50 kW median £1,262 per kW | Small sites or a first system on a modest roof |
| 100 kWp | £750 to £1,050 | £75,000 to £105,000 | OVO: £700 to £1,100+; Solar4Good: £800 to £850 | Mid-size roofs with steady daytime demand |
| 250 kWp | £720 to £1,000 | £180,000 to £250,000 | No second public source | Single-site manufacturers and distributors |
| 500 kWp | £700 to £960 | £350,000 to £480,000 | No second source opened | Large roofs and multi-shift operations |
Spirit Energy publishes total installed cost ranges. The per-kWp column divides those totals by system size. Treat the ranges as a planning guide for a first board discussion, not a quote. A tender on your actual roof replaces them with comparable prices.
What makes two quotes for the same roof differ?
Quotes for the same roof differ mainly because of roof type, scaffolding and access, the number of inverters, grid connection work and any roof repairs, and they should be itemised so you can see which applies.
OVO and Solar4Good name overlapping drivers 34.
- Roof type. Ballasted flat-roof framing and rail systems on pitched roofs are priced differently, and a complex roof adds labour.
- Scaffolding and access. Tall buildings and awkward access raise the cost before a panel is fitted.
- Inverters. The number and type of inverters changes the equipment line and the replacement cost later.
- Grid connection. Electrical connection upgrades and the DNO application under G99 add cost and time. Solar4Good gives 6 to 12 weeks for G99 approval. OVO says the G99 application is included in installer quotes, so ask whether yours is.
- Roof works. Existing electrical infrastructure and roof condition matter. A roof that needs repair or over-cladding costs more than a sound one.
No public source we found gives a typical G99 application fee or DNO connection charge. Business Solar Check, a lead-generation site, puts DNO fees at about £1,000 to £10,000 or more, without giving a method 6. Ask each installer to state them separately. Our guide to timeline and grid connection covers G98 and G99 in more detail.
Is VAT charged on commercial solar panels in the UK?
Yes, commercial solar installation is standard-rated at 20% VAT, and the 0% rate applies only to residential accommodation and certain charitable buildings.
HMRC Notice 708/6 sets out the 0% relief for energy-saving materials. It covers residential accommodation and, from 1 February 2024, buildings used solely for a relevant charitable purpose 5. The notice does not name offices or factories, so solar on those buildings is not covered by the relief.
Solar4Good also states that commercial solar carries 20% VAT and that VAT-registered businesses can usually reclaim it 4. Check your reclaim position with your accountant, including any partial exemption. This guide is not tax advice.
Prices in this guide are ex-VAT. Check that every quote you receive states whether VAT is included.
When is a cost comparison not worth the effort?
A formal cost comparison is not worth it for a small or simple system, or when you already hold comparable quotes and trust your installer.
If your roof is small, simple and well within the 50 kWp range, a local MCS installer and one or two quotes may be enough. The price spread between installers matters most as system size grows, because a spread of £100 per kWp is £25,000 on 250 kWp.
If you already hold three quotes on the same specification and trust one installer, a further tender may add little. If the roof is leased with a short term remaining, or daytime demand is low, the cost question comes second to whether solar suits the site. Our guide on site suitability covers those checks.
Illustrative example
Budgeting a 250 kWp roof
This example uses Spirit Energy's 2026 per-kWp range for 250 kWp and shows the arithmetic 2. It is not a quote.
- Low end: 250 kWp x £720 = £180,000 ex-VAT.
- High end: 250 kWp x £1,000 = £250,000 ex-VAT.
- VAT at 20%: £36,000 to £50,000, so £216,000 to £300,000 including VAT, before any reclaim.
- Add £2,000 to £10,000 for an inverter replacement after 10 to 15 years 3.
The spread between the low and high end is £70,000, or 39% above the low figure. That spread is the reason to compare quotes on the same scope.
Your next steps
Set a planning range Multiply your roof's likely kWp by the installer ranges above, ex-VAT, so the board sees a range rather than a single number.
Ask for itemised quotes Require roof works, scaffolding, inverters, G99 and DNO costs and VAT to be listed as separate lines.
Compare on one basis Put every quote on kWp (DC), scope and warranty before you look at price.
Confirm VAT with your accountant Check your reclaim position before the board sees a net figure.
How CH Group handles this
We know a board cannot approve a number it cannot check.
CH Group verifies twelve months of half-hourly data first, so the system is sized to your actual demand. We then run one controlled tender to our panel of vetted installer partners, and every proposal is compared on the same ten variables, including £/kWp, equipment, warranties and programme. Every partner bids against the same brief.
The result is like-for-like prices on your roof rather than a range. Real projects on our projects page show projected results, for example a 150 kWp system with £25,182 projected annual savings and a 2.8 years projected payback.
Questions buyers ask next
Why is DESNZ cost data higher than installer prices?
The DESNZ figure is for its 10 to 50 kW band, built from MCS-registered jobs, including smaller commercial and domestic-type installs. It is not a price for a 250 kWp roof.
Does the price per kWp include the grid connection?
Not always. OVO says the G99 application is included in installer quotes, but connection upgrades and DNO charges may sit outside a headline price. Ask each installer to list them as separate lines.
Can a business reclaim the VAT on solar panels?
VAT-registered businesses can usually reclaim the 20% VAT on commercial solar, according to Solar4Good. Your accountant should confirm your position, including any partial exemption.
Is there a grant for commercial solar in the UK?
The UK Shared Prosperity Fund ended on 31 March 2026, so some answers online are out of date. See our funding guide and the funding section of our businesses page for the routes that remain.
What costs come after installation?
The main planned cost is inverter replacement after 10 to 15 years, at £2,000 to £10,000 according to OVO. Ask your installer for a maintenance and warranty schedule before you sign.
Sources
Public figures are from the sources below, as published on the dates shown. CH Group project figures are projections supplied for each case study. This guide is general information, not financial, tax or legal advice.
- DESNZ, Small-scale solar PV cost data 2025-26, 28 May 2026.
- Spirit Energy, Commercial solar cost, payback and ROI, 2026.
- OVO Solar & Heating, Commercial solar panels cost, 4 Nov 2026.
- Solar4Good, 100kW Solar System UK: The Complete 2026 Guide for Large Commercial Sites, 2 May 2026.
- HMRC, VAT on energy saving materials and heating equipment (VAT Notice 708/6), 31 Jan 2024.
- Business Solar Check, How to compare commercial solar quotes (12-point checklist), June 2026.
- Enterprise Nation, Article on the UK Shared Prosperity Fund replacement, 17 Mar 2026.